The High Cost of Ignoring Defect Complaints for Residential Builders

A recent $2 million Supreme Court decision highlights the costly consequences for residential builders who fail to respond reasonably and promptly to defect complaints—especially when trust with the homeowner breaks down.

In disputes regarding residential building work, it is common for a homeowner to seek that any defects in the work are rectified by a third party rather than the original builder.

In extreme cases, a homeowner may entirely refuse to give the builder an opportunity to rectify alleged defects.

A recent decision of the NSW Supreme Court provides an example of exactly this scenario, where the builder’s own actions resulted in it having to pay the plaintiff almost $2M to cover rectification works completed by a third party.

The Court’s decision offers guidance to builders as to when a homeowner will be entitled to refuse to give the builder an opportunity to rectify alleged defects.

Background

The Owners – Strata Plan No 89074 v Ceerose Pty Ltd [2024] NSWSC 1494 (Ceerose), concerned a claim by the owners corporation of a 16-storey apartment building against the builder and developer of that building, in respect of alleged breaches of the statutory warranties implied by Section 18B of the Home Building Act 1989 (NSW).

One of the defences advanced by the defendants was that they had sought the plaintiff’s consent to undertake rectification works, however the plaintiff had refused to allow the builder to do so and had instead engaged another builder to perform the rectification works.

The defendants contended that:

  1. the plaintiff had failed to mitigate the loss it had suffered, by not allowing the defendants to undertake the rectification works.
  2. The plaintiff should not be entitled to recover the rectification costs it had incurred at all, as had the plaintiff acted in a “reasonably prudent” way (i.e. allowed the builder to rectify the defects) no loss would have arisen.

The issue

The key issue was whether the plaintiff had in fact failed to mitigate its loss by unreasonably refusing access to carry out rectification works.

The decision

The Court ultimately found that the plaintiff had not failed to mitigate its loss and entered judgment for the plaintiff in the amount of $1,952,984 (exclusive of GST).

Key to the Court’s decision were the following findings:

  1. There is no positive duty to mitigate loss, but rather a ‘duty’ on the part of the plaintiff not to act unreasonably.
  2. In assessing loss for breach of contract, loss which is due to unreasonable or improvident actions of the plaintiff will not be recoverable.
  3. What is reasonable for a person to do in mitigation of damages is a question of fact in the circumstances of each case.
  4. In the particular circumstances of this case, the owners did not act unreasonably in refusing to allow the defendants access to carry out further work, as they were justified in having lost confidence in the defendants due to a combination of:
    1. the defendants’ prior inadequate repairs;
    2. the defendants’ failure to engage with the method of rectification proposed by the plaintiff’s expert;
    3. the seriousness of the defects; and,
    4. the lack of progress in negotiations with the defendants.

Key Insights

The key takeaway of the Court’s decision was its consideration of the following factors in assessing whether the plaintiff had acted unreasonably :

  1. the extent and seriousness of the defects;
  2. the quality of any repairs effected by the builder;
  3. the builder’s engagement with the owner in respect of the suggested defects and proposed method of rectification, in short, has the builder responded in a timely manner, taken the complaints seriously and acted fairly; and
  4. the efficacy or perceived futility of continuing to negotiate with the builder.

These factors are likely to be taken into account in future decisions in which allegations are made that a homeowner has acted unreasonably.

For builders and homeowners alike, Ceerose serves as a reminder of the importance of a builder maintaining the trust and confidence of a homeowner from the commencement of a build. Where a homeowner alleges the existence of defects, their concerns should be taken seriously and addressed (and, if necessary, defects rectified) by their builder in a timely manner.

Should a builder fail to do so, the homeowner may be entitled to deny the builder the opportunity to perform rectification works, and engage a third party and seek recovery of the rectification costs under the Home Building Act 1989 (NSW).

A $2M Supreme Court decision shows how quickly things can go wrong when defect complaints aren’t taken seriously

When a builder finishes a job and the homeowner finds defects, the builder is usually given the chance to come back and fix the issues. But what happens when the homeowner doesn’t trust the builder anymore and hires someone else to do the repairs?

A recent case in the NSW Supreme Court shows exactly how this can play out—and the result wasn’t good for the builder.

What Happened?

In the case of The Owners – Strata Plan No 89074 v Ceerose Pty Ltd, the owners of a 16-storey apartment building sued the builder for defective work under the Home Building Act 1989 (NSW). Instead of allowing the original builder to fix the defects, the owners hired a third party to complete the repairs—and then claimed back nearly $2 million in costs.

The builder argued that the owners didn’t give them a fair chance to return and fix the problems, and therefore should not be allowed to recover those costs.

What Did the Court Decide?

The Court disagreed with the builder. It found that the owners were justified in refusing access, and the builder was ordered to pay $1.95 million in rectification costs.

The Court said that while homeowners don’t have a duty to help the builder minimise losses (known as “mitigating loss”), they also can’t behave unreasonably. In this case, the Court found the owners acted reasonably based on a few key points.

Why the Homeowners Were Justified

The Court pointed to four major reasons why the owners were right to hire someone else:

  1. Serious Defects – The problems with the building were significant.
  2. Poor Previous Repairs – The builder had already attempted repairs that weren’t good enough.
  3. No Engagement – The builder didn’t take the owners’ expert advice seriously.
  4. Lack of Progress – There were delays and little movement toward a resolution.

Together, these reasons gave the owners good reason to lose trust in the builder and take matters into their own hands.

What This Means for Builders

This case is a big warning for builders—especially in the residential space.

If a homeowner raises concerns about defects, you need to:

  • Act quickly
  • Take the complaint seriously
  • Communicate clearly and consistently
  • Engage in good faith to fix the problem

If you don’t, the homeowner might be allowed to bring in someone else and recover the full cost of repairs from you.

Even if you believe you’re in the right, the Court will look at whether you behaved reasonably, fairly, and professionally.

Key Takeaways for Builders

The Court will consider things like:

  • How bad the defects are
  • Whether you’ve already tried to fix them—and how well you did
  • How seriously you took the owner’s concerns
  • Whether ongoing negotiations were going anywhere

If trust breaks down and it’s your fault, you could be left with a massive bill, even if you were originally willing to fix the problem.

Building and Construction Lawyers for Sydney and Newcastle

Need Answers Fast? Contact Us Today

The information in this article is not legal advice and is intended to provide commentary and general information only. It should not be relied upon or used as a definitive or complete statement of the relevant law. You should obtain formal legal advice specific to your particular circumstance. Liability limited by a scheme approved under Professional Standards Legislation.

Author
Special Counsel
Accredited Specialist (Commercial Litigation)